Stage 3/4 Turnaround Feb – Sep 2005
Units Visbreaker, VDU &
Sulphur Recovery
Execution of mechanical Turnaround including Equipment items Fired Heater, Columns, Drums, Exchangers, Valves, Pipework and Major Capital Items.
Expected Man-hour 45,000
Peak Labour 160