Client – Artenius UK

T8 Shutdown March 2008-Wilton Site 

  • Main Mechanical Contractor
  • Workscope included pre-fabrication & installation of exotic pipework, removal & reinstatement of over 400 pressure relief, non-return & control valves. Vessel inspection & repair and all mechanical activities.
  • Peak Labour 280
  • Value: £1.8m